Question: You calculate the estimate at completion for a project at the 9 0 % completion milestone and it is $ 7 5 , 0 0

You calculate the estimate at completion for a project at the 90% completion milestone and it is $75,000 for a project that is budgeted at $73,000. What is the variance at completion?
-$6,570
-$2,000
$2,000
$6,570