Question: You continue working on your project according to plan even though you know that half of the people on your team may leave soon to
You continue working on your project according to plan even though you know that half of the people on your team may leave soon to pursue other opportunities. What risk response strategy are you using?
A. Mitigation
B. Transference
C. Acceptance
D. Avoidance