Question: You find an activity network with the calculation based on the critical path method. However, the figure is damaged, and you only have the partial
You find an activity network with the calculation based on the critical path method. However, the figure is damaged, and you only have the partial information as below. Suppose the time unit is an hour. Which of the following statements is NOT CORRECT according to this figure? The project completion time is 15 hours. There exists one activity with the earliest completion time equal to 12 There exists one activity with the latest start time equal to 15 Activity B is a critical activity