Question: You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.75, CPI = 1.0 The project has been
You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.75, CPI = 1.0
| The project has been cancelled while it was executed. At that time the project was behind schedule and on budget. | ||
| The project's deliverables have all been finished. The project came in ahead of schedule but on budget. | ||
| The project's deliverables have all been finished. The project came in on schedule but over budget. | ||
| The project's deliverables have all been finished. The project came in behind schedule but on budget. |
Option A is incorrect, I think D would b next best?