Question: You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.75, CPI = 1.0 1. The project has
You found the following earned value analysis information for a project that was recently closed-out: SPI = 0.75, CPI = 1.0
1. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
2. The project's deliverables have all been finished. The project came in behind schedule but on budget.
3. The project's deliverables have all been finished. The project came in on schedule but over budget.
4. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.