Question: You had to estimate certain activity durations as the project manager of a manufacturing facility construction project before you could hire all of the project

You had to estimate certain activity durations as the project manager of a manufacturing facility construction project before you could hire all of the project team members. You discover that the actual skill levels of the project team members are substantially lower than what you had anticipated when estimating the activity durations throughout the acquisition process. In this case, what is the best course of action