Question: You have been asked to construct a project network for a warehouse, which aims to automate its order picking system, for the activities below: Activity
You have been asked to construct a project network for a warehouse, which aims to automate its order picking system, for the activities below:
| Activity | Description | Preceding Activity | Days |
| A | Define Requirements | None | 10 |
| B | Assign Team | A | 5 |
| C | Design Hardware | A | 25 |
| D | Code Software | B | 20 |
| E | Build & Test Hardware | C | 50 |
| F | Develop Patent Request | C | 15 |
| G | Test Software | D | 35 |
| H | Integrate Systems | E, F, G | 15 |
- 4.0 points to construct project network diagram.
- 1.5 points to determine the critical path and show your working.
- 1.0 points: You are a Project Manager. In your weekly progress meeting, you found out that activity E will have a delay of 3 days. Activity F may also have 13 days delay. As a project manager, which of these activities would you try to work on so that you can overcome potential problem and do not have any delay?
- 1.0 points: For your choices in the above question, explain your answers (use examples where appropriate).