Question: You have been hired to design User Interface for a Web Site that has four web pages. Each web page is scheduled to take one
You have been hired to design User Interface for a Web Site that has four web pages. Each web page is scheduled to take one day to complete at a cost of $600 per web page. At the end of day 2, you have spent $1100 and 1.5 pages are complete.
How is the project doing? Select all that apply. Be quick please
| Under budget | ||
| Over budget | ||
| Ahead of Schedule | ||
| Behind Schedule |