Question: You have collected the data for a Time - Cost CPM Scheduling model analysis. The time is in days and the project direct costs are
You have collected the data for a TimeCost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below.
The indirect costs for the project are determined on a daily duration basis. If the project lasts days the total indirect costs are $ days they will be $ days they will be $ and days they will be $ If you crash this project by one day what is the total ie direct and indirect project cost?
Activity Immediate Predecessor Normal Time Crash Time Normal CostDirect Crash CostDirect
A None $ $
B A $ $
C A $ $
D B and C $ $
E D $ $
F E $ $
G F $ $