Question: You have collected the following data based on three months of your project s performance. Complete the table. Calculate cumulative CPI ( CPIC ) .

You have collected the following data based on three months of your projects performance.
Complete the table. Calculate cumulative CPI (CPIC). How is the project performing after these
three months? Is the trend positive or negative?
EV EV C AC AC C CPI CPI C
January $30,000 $35,000
February $95,000 $100,000
March $125,500 $138,000
Overall, the project is performing below required levels (assuming CPI should equal 1.0 or
higher). However, the original poor value is trending moderately better (moving from 0.86
to 0.92 over three months). Trend is positive but the CPI is still under-performing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!