Question: You have collected the following data based on three months of your projects performance. Complete the table. Calculate cumulative CPI (CPIC). How is the project
.png)
EV EVC ACC CPI AC $35,000 $100,000 $138,000 CPIC January$30,000 February | $95,000 March $125,500
Step by Step Solution
3.43 Rating (162 Votes )
There are 3 Steps involved in it
EV EV C AC AC C CPI CPI C January 30000 30000 35000 35000 086 086 February 95000 ... View full answer