Question: You have the below information about your project, please implement the Earned Value Management and calculate the below varies measures of works. (8 Points Total)

You have the below information about your project, please implement the Earned Value Management and calculate the below varies measures of works. (8 Points Total)

Activity

Predecessors

Duration (days)

Activity Total Cost

Cost per Day ($)

A

-

10

$1000

$100

B

A

11

$1320

$120

C

A

9

$450

$50

D

C

4

$320

$80

E

D

14

$1400

$100

F

E

13

$1300

$100

The measures of Day 21 are as below

Day 21 Measures

Activity

Actual Cost

Actual Completion (%)

Planned Value (PV)

Earned Value (EV)

A

$1100

100%

B

$1350

80%

C

$470

100%

D

$200

50%

E

0

0

F

0

0

Total

Project Day 21 Summary

Measures

Comments

PV

EV

AC

BAC

CV

CPI

SV

SPI

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!