Question: You have the below information about your project, please implement the Earned Value Management and calculate the below varies measures of works. (8 Points Total)
You have the below information about your project, please implement the Earned Value Management and calculate the below varies measures of works. (8 Points Total)
| Activity | Predecessors | Duration (days) | Activity Total Cost | Cost per Day ($) |
| A | - | 10 | $1000 | $100 |
| B | A | 11 | $1320 | $120 |
| C | A | 9 | $450 | $50 |
| D | C | 4 | $320 | $80 |
| E | D | 14 | $1400 | $100 |
| F | E | 13 | $1300 | $100 |
The measures of Day 21 are as below
| Day 21 Measures | ||||
| Activity | Actual Cost | Actual Completion (%) | Planned Value (PV) | Earned Value (EV) |
| A | $1100 | 100% |
|
|
| B | $1350 | 80% |
|
|
| C | $470 | 100% |
|
|
| D | $200 | 50% |
|
|
| E | 0 | 0 |
|
|
| F | 0 | 0 |
|
|
| Total |
|
|
|
|
| Project Day 21 Summary | ||
| Measures | Comments | |
| PV |
|
|
| EV |
|
|
| AC |
|
|
| BAC |
|
|
| CV |
|
|
| CPI |
|
|
| SV |
|
|
| SPI |
|
|