Question: You is performing Earned Value technique on a project after 2 weeks. Data appears as below PV=200 EV=135 AC=150 What is the cost variance (CV)?
You is performing Earned Value technique on a project after 2 weeks. Data appears as below PV=200 EV=135 AC=150 What is the cost variance (CV)? -1