Question: You is performing Earned Value technique on a project after 2 weeks. Data appears as below PV = 2 0 0 EV = 1 3

You is performing Earned Value technique on a project after 2 weeks. Data appears as below
PV=200 EV=135 AC=150
What is the schedule variance (SV)?
35
-65
50
-15