Question: You may need to use the appropriate technology to answer this question. completion date requested by the owner. The Mueller project manager prepared the following

 You may need to use the appropriate technology to answer thisquestion. completion date requested by the owner. The Mueller project manager prepared

You may need to use the appropriate technology to answer this question. completion date requested by the owner. The Mueller project manager prepared the following project network. Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. (a) Find the critical path. (Enter your answers as a comma-separated list.) (b) What is the expected project completion time (in weeks)? weeks places.) (e) What should the construction company tell the owner? (Enter your free-form answer using as many characters as necessary.) Based on the critical path and the expected 52-week completion time, the construction company should let the owner know that the project may take longer than the 42 weeks that were ordered or requested. They should also tell the owner how likely it is that the project will be done in 42 weeks (0.5%) and how likely it is that it will be done more than 3 months late (17.61\%). The company should talk to the owner about ways to speed up the project plan and push back Score: 1 out of 1 Comment

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!