Question: You must analyze two projects, X and Y. Each project costs $10,000 and the firms WACC is 14%. The expected cash flows are as follows:
You must analyze two projects, X and Y. Each project costs $10,000 and the firms WACC is 14%. The expected cash flows are as follows:
|
| 0 | 1 | 2 | 3 | 4 |
| Project X | -20000 | 11000 | 7000 | 6000 | 5000 |
| Project Y | -20000 | 8000 | 7500 | 7000 | 6500 |
(a.) Calculate each project Xs NPV, MIRR, and discounted payback.
(b.) Calculate each project Ys IRR and payback.
(c.) Which project(s) should be accepted if they are independent?
(d.) Which project(s) should be accepted if they are mutually exclusive?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
