Question: You must schedule 4 tasks on a single machine, with symmetric sequence-dependent setup times. The setup times are given in the table below: From/To 1

You must schedule 4 tasks on a single machine,
You must schedule 4 tasks on a single machine, with symmetric sequence-dependent setup times. The setup times are given in the table below: From/To 1 9 10 2 3 1 6 22 2 6 0 18 12 13 3 10 0 18 12 4 2 13 0 Use the closest insertion algorithm to find a good sequence