Question: what is the total time for the sequence? You must schedule 4 tasks on a single machine, with asymmetric sequence dependent setup times. The setup

what is the total time for the sequence?
what is the total time for the sequence? You must
You must schedule 4 tasks on a single machine, with asymmetric sequence dependent setup times. The setup times are given in the table below: From/To 2 3 4 18 10 4 1 0 15 ON 6 13 9 4 2 13 15 4 3 18 5 21 0 0 8 13 4 5 12 20 16 9 0 0 12 5 7 14 0 13 3 12 6 15 5 Use the closest insertion algorithm to find a good sequence