Question: You must schedule 4 tasks on a single machine, with symmetric sequence-dependent setup times. The setup times are given in the table below: From To

You must schedule 4 tasks on a single machine,

You must schedule 4 tasks on a single machine, with symmetric sequence-dependent setup times. The setup times are given in the table below: From To 1 2 3 4 1 0 6 10 2 2 6 0 18 12 3 10 18 0 13 4 2 12 13 0 Use the closest insertion algorithm to find a good sequence