Question: You need to develop a labor time estimate for a customer order of 2 0 network installations. It is estimated that the first installation will

You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require 40 hours of labor and a learning curve of 70 percent is expected. If the average labor costs is $25, what is the total labor cost for installing the networks?