Question: You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require
You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require 50 hours of labor and a learning curve of 70 percent is expected. 1.How many labor-hours are required for the fifteenth installation?
Answer :
No. of labor hours required to 15th installation.
T15 = T1C = T1*C15unit time
C15 value for 70% leaving curve is 0.2482
T15 = 50 0.2482 = 12.41
No. of labor hours required to 15th installation is 12.41 Hrs.
Could you please help me, How to calculate the C15 C15 value for 70% leaving curve?
2.How many labor hours are required for the twentieth installation?