Question: You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require

You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require 50 hours of labor and a learning curve of 70 percent is expected. 1.How many labor-hours are required for the fifteenth installation?

Answer :

No. of labor hours required to 15th installation.

T15 = T1C = T1*C15unit time

C15 value for 70% leaving curve is 0.2482

T15 = 50 0.2482 = 12.41

No. of labor hours required to 15th installation is 12.41 Hrs.

Could you please help me, How to calculate the C15 C15 value for 70% leaving curve?

2.How many labor hours are required for the twentieth installation?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!