Question: You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require

You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require 60 hours of labor and a learning curve of 90% is expected.

(a) How many labor hours are required for the 15" installation?

(b) How many labor hours are required for the 20" installation?

(c) How many labor hours are required to complete all 20 installations?

(d) If the average labor cost is $32.00, what is the total labor cost for installing the networks?