Question: You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require

You need to develop a labor time estimate for a
You need to develop a labor time estimate for a
You need to develop a labor time estimate for a
You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require 40 hours of labor and a learning curve of 75 percent is expected. Table 11.9 Learning Curve Coefficients 70% 75% 80% 85% 90% Unit Unit Number Unit Time Total Time Unit Time Total Time Total Time Unit Time Total Time Unit Time Total Time Time 1 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 1.000 2 700 92.700 750 1.750 800 1.800 850 1850 900 1.900 3 568 2268 634 2.384 702 2.502 773 2623 846 2.746 4 490 2.758 562 2.946 640 3.142 .723 3.345 810 3.556 5 437 3.195 .513 3.459 596 3.738 .686 4,031 1783 4339 6 398 3:593 475 3.934 562 4.299 657 4.688 762 5.101 7 367 3.960 446 4.380 534 4.834 634 5:322 744 5.845 8 .343 4.303 422 4.802 .512 5.346 .614 5.936 .729. 6.574 9 323 4.626 .402 5.204 493 5.839 .597 6.533 716 7.290 10 1306 4.932 385 5.589 477 6.315 .583 7.116 .705 7.994 11 1291 5.223 1370 5.958 462 6.777 .570 7.686 .695 8.689 12 278 5.501 357 6.315 449 7.227 558 8.244 .685 9.374 13 .267 5.769 345 6.660 438 7.665 .548 8.792 -677 10.052 14 257 6.026 334 6.994 .428 8.092 539 9.331 .670 10.721 15 248 6.274 325 7.319 .418 8.511 530 9.861 .663 11.384 16 240 6.514 1:316 7.635 410 8.920 .522 10.383 656 12.040 17 233 6.747 309 7.944 402 9.322 515 10.898 650 12.690 18 226 6.973 301 8.245 394 9.716 .508 11.405 .644 13.334 19 220 7.192 295 8.540 388 10.104 501 11.907 639 13.974 20 214 7.407 288 8.828 1381 10.485 495 12.402 .634 14.608 21 209 7.615 283 9.111 375 10.860 490 12.892 630 15.237 22 204 7.819 277 9.388 1370 11.230 484 13.376 625 15.862 23 199 8.018 272 9.660 1364 11.594 479 13.856 .621 16.483 24 195 8.213 267 9.928 359 11.954 475 14.331 617 17.100 25 191 8.404 263 10.191 355 12.309 470 14.801 .613 17.713 (a) Your answer is incorrect How many tabor hours are required for the fifteenth installation? hours (Round your answer to 2 decimal places, eg,5.12.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!