Question: You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require
You need to develop a labor time estimate for a customer order of 20 network installations. It is estimated that the first installation will require 60 hours of labor, and a learning curve of 90 percent is expected.
How many labor-hours are required for the fifteenth installation?
How many labor-hours are required for the twentieth installation?
How many labor-hours are required to complete all 20 installations?
If the average labor cost is $32, what is the total labor cost for installing the networks?