Question: You operate a process with three workstations; the cycle times are given below. A regular batch is 52 units and your production line runs 5
You operate a process with three workstations; the cycle times are given below. A regular batch is 52 units and your production line runs 5 hours per day.
Workstation 1 has a cycle time of 2 minutes per unit
Workstation 2 has a cycle time of 3 minutes per unit
Workstation 3 has a cycle time of 3 minutes per unit
Calculate how many hours lead time is required to ship a batch, assuming there are no orders ahead in the queue and there is no inventory to fill the order.