Question: You operate a process with three workstations; the cycle times are given below. A regular batch is 52 units and your production line runs 5

You operate a process with three workstations; the cycle times are given below. A regular batch is 52 units and your production line runs 5 hours per day. Calculate how many hours lead time is required to ship a batch, assuming there are no orders ahead in the queue and there is no inventory to fill the order.

Workstation 1 has a cycle time of 2 minutes per unit

Workstation 2 has a cycle time of 3 minutes per unit

Workstation 3 has a cycle time of 3 minutes per unit

Select one:

a. 1560.00

b. 8.00

c. 1560.00

d. 90.00

e. 2340.00