Question: You operate a process with three workstations; the cycle times are given below. A regular batch is 60 units and your production line runs 6

You operate a process with three workstations; the cycle times are given below. A regular batch is 60 units and your production line runs 6 hours per day. Calculate how many hours lead time is required to ship a batch, assuming there are no orders ahead in the queue and there is no inventory to fill the order.

Using the same process times as in the previous question, calculate the most units (batch size of 10) that you can ship within one day. Assume your workstations dont share equipment or resources.

Workstation 1 has a cycle time of 6 minutes per unit

Workstation 2 has a cycle time of 3 minutes per unit

Workstation 3 has a cycle time of 2 minutes per unit

Select one:

a. 7

b. 11

c. 5

d. 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!