Question: You perform an earned value analysis for your project, resulting in the following numbers: EV: 354,000; PV: 454,000; AC: 474,000. Which results are correct? a.
You perform an earned value analysis for your project, resulting in the following numbers:
EV: 354,000; PV: 454,000; AC: 474,000. Which results are correct?
a.
CV: -120,000; SV: -100,000
b.
CV: +100,000; SV: +120,000
c.
CV: +120,000; SV: +100,000
d.
CV: -100,000; SV: -120,000