Question: Your cost analyst has calculated that your project has an estimate at completion of $ 4 5 0 , 0 0 0 . Given that

Your cost analyst has calculated that your project has an estimate at completion of $450,000. Given that you know that the project budget is $425,000 what can you infer about the project's cost performance index results up to this point?
A: Cost performance index is above 1
B: Cost performance index is below 1
C: There is not sufficient information to infer
D: Cost performance index is 1