Question: Your crew has 3 2 , 5 8 0 square feet of metal panel to install on the exterior of a building. You need to

Your crew has 32,580 square feet of metal panel to install on the exterior of a building. You need to complete this work in 20 working days. Each working day is 10 hours long. For each crew member, one half hour of each day is spent completing the job safety analysis and morning stretching.Yourcompany's cost history database reports that each crew member typically installs 45 square feet of metal panel per hour. Given these parameters, how many people minimum do you need on site to complete this work in the allotted time?