Question: Your program manager has advised that you must protect the organisation from financial risk. In planning a new project, you realise there is a limited
Your program manager has advised that you must protect the organisation from financial risk. In planning a new project, you realise there is a limited scope definition related to the work needed to fulfil the contract. What is the best type of contract to choose?
a Fixedprice FP
b Cost plus percentage of cost CPPC
c Cost plus fixed fee CPFF
d Target cost
Step by Step Solution