Question: Your program manager has advised that you must protect the organisation from financial risk. In planning a new project, you realise there is a limited

Your program manager has advised that you must protect the organisation from financial risk. In planning a new project, you realise there is a limited scope definition related to the work needed to fulfil the contract. What is the best type of contract to choose?
a. Fixed-price (FP)
b. Cost plus percentage of cost ( CPPC)
c. Cost plus fixed fee (CPFF)
d. Target cost
 Your program manager has advised that you must protect the organisation

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!