Question: 25. Your program manager has advised that you need to protect the organization from financial risk. In / planning a new project, you realize t_h!re
25. Your program manager has advised that you need to protect the organization from financial risk. In
/ planning a new project, you realize t_h!re is limited scope definition related to the work needed to fulfill the contract. What is the best type of contract to choose?
A. Fixed-price (PP)
B. Cost plus p.:rcentage of cost (CPPC)
C. Tiine •md material (T&M)
D. Cost plus fixed fee (CPFF)
/