Question: Your project has a critical path equal to 30 days and a standard deviation of 2 days.What will be the earliest finish for this project
Your project has a critical path equal to 30 days and a standard deviation of 2 days.What will be the earliest finish for this project within a 95% confidence level?
A) 10 days
B) 15 days
C) 20 days
D) 25 days