Question: Your project has a critical path equal to 30 days and a standard deviation of 2 days. What will be the latest finish estimates for
Your project has a critical path equal to 30 days and a standard deviation of 2 days. What will be the latest finish estimates for this project within a 95% confidence level?
Your project has a critical path equal to 30 days and a standard deviation of 2 days. What will be the latest finish estimates for this project within a 95% confidence level?
A) 30 days
B) 40 days
C) 35 days
D) 45 days