Question: Your project has a critical path equal to 3 0 days and a standard deviation of 2 ( 1 ) / ( 2 ) days.What

Your project has a critical path equal to 30 days and a standard deviation of 2(1)/(2) days.What will be the earliest finish for this project within a 95% confidence level?
Your project has a critical path equal to 30 days and a standard deviation of 2(1)/(2) days.What will be the earliest finish for this project within a 95% confidence level?
10 days
15 days
20 days
25 days