Question: Your project has a network diagram. Two ( 2 ) of the activities, are D and E . Both activities, Activity D and Activity E
Your project has a network diagram. Two of the activities, are D and E Both activities, Activity D and Activity E point to a common successor, Activity F Activity D will be completed in week, Activity E will be completed in weeks. Activity D can wait for a short time nonspecified without affecting the early start of Activity F The flexibility in delayed time between Activity D and Activity F is known as:
Question options:
PERT
Free Float or free slack
Critical time
SMART