Question: Your project has a network diagram. Two ( 2 ) of the activities, are D and E . Both activities, Activity D and Activity E

Your project has a network diagram. Two (2) of the activities, are D and E. Both activities, Activity D and Activity E point to a common successor, Activity F. Activity D will be completed in 1 week, Activity E will be completed in 2 weeks. Activity D can wait for a short time (non-specified) without affecting the early start of Activity F. The flexibility in delayed time between Activity D and Activity F is known as:
Question 12 options:
PERT
Free Float (or free slack)
Critical time
S.M.A.R.T