Question: Your project is executing under budget. This is consistent with which one of the following scenarios? a) EV is 100 , and AC is 120.
Your project is executing under budget. This is consistent with which one of the following scenarios? a) EV is 100 , and AC is 120. b) PV is 100 , and EV is 120. c) PV is 120 , and AC is 100 . d) AC is 100 , and EV is 120