Question: Your project is to replace the legacy system and install a new cloud - based system. Your PMO has provided all methodologies and templates and

Your project is to replace the legacy system and install a new cloud-based system. Your PMO has provided all methodologies and templates and is leaving it up to
you as a project manager to follow those procedures. If you feel that some procedures need to be improved the PMO will work with you to make those
improvements. Most likely what type of PMO does this describe?
A
Micromanaging PMO
B
Directive PMO
C
Controlling PMO
D
Supportive PMO