Question: Your project management plan results in a project schedule that is too long If the project network diagram cannot change but you have extra personnel
Your project management plan results in a project schedule that is too long If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do
Group of answer choices
Crash the project.
Monte Carlo analysis.
Fast track the project.
Level the resources.