Question: Your project management plan results in a project schedule that is too long If the project network diagram cannot change but you have extra personnel

Your project management plan results in a project schedule that is too long If the project network diagram cannot change but you have extra personnel resources, what is the BEST thing to do?

  • A-) Fast track the project.
  • B-) Level the resources.
  • C-) Crash the project.
  • D-) Monte Carlo analysis.