Question: Your project management plan results in a project schedule that is too long. If two activities that are currently sequentially ordered can be done in
Your project management plan results in a project schedule that is too long. If two activities that are currently sequentially ordered can be done in parallel, what is the BEST thing to do? Group of answer choices Fast-track the project Level the resources Crash the project Monte Carlo analysis