Question: Your project schedule is too long. If the project network diagram cannot change, but you have extra personnel resources, what is the BEST thing to

Your project schedule is too long. If the project network diagram cannot change, but you have extra personnel resources, what is the BEST thing to do:
Question 10 options:
Assign additional resources
Fast track the project
Level the resources
Monte Carlo analysis