Question: Your project schedule is too long. If the project network diagram cannot change, but you have extra personnel resources, what is the BEST thing to
Your project schedule is too long. If the project network diagram cannot change, but you have extra personnel resources, what is the BEST thing to do:
Question options:
Assign additional resources
Fast track the project
Level the resources
Monte Carlo analysis
Step by Step Solution
There are 3 Steps involved in it