Question: Your project's schedule performance index (SPI) is 0.9. Your earned value (EV) is $9000, and your actual cost (AC) is $9,500. What is the planned

Your project's schedule performance index (SPI) is 0.9. Your earned value (EV) is $9000, and your actual cost (AC) is $9,500. What is the planned value?

Group of answer choices

a. $10,000

b. $10,556

c. $8100

d. $8550