Question: Your team is hard at work on their assigned project tasks when one team member discovers a risk that was not identified during risk planning.
Your team is hard at work on their assigned project tasks when one team member discovers a risk that was not identified during risk planning. What is the FIRST thing to do?
a. Halt work on the project.
b. Assess the risk.
c. Update the risk management plan.
d. Look for ways to mitigate the risk. Save Answer