Question: You're managing a project to install 200 windows in a new skyscraper and need to figure out your budget. Each week of the project costs
You're managing a project to install 200 windows in a new skyscraper and need to figure out your budget. Each week of the project costs the same: your team members are paid a total of $4,000 every week, and you need $1,000 worth of parts each week to do the work. If the project is scheduled to last 16 weeks. You've checked with your team, but they have bad news. The schedule says they were supposed to have installed 50 windows by now, but they've only installed 40. What is the earned value be right now?