Question: In your project documentation, where would the reporting methods and frequency most likely be outlined? a) Communications management plan b) Communications requirement strategy c) Stakeholder
In your project documentation, where would the reporting methods and frequency most likely be outlined?
a) Communications management plan
b) Communications requirement strategy
c) Stakeholder management plan
d) Stakeholder requirement strategy