Question: 4. (**) Now reconsider the project in Problem 3. Every day the project goes on costs the company $5,000 in overhead costs. One of the

4. (**) Now reconsider the project in Problem 3. Every day the project goes on costs the company $5,000 in overhead costs. One of the managers responsible for carrying out Activity E feels she can crash the activity by 1 day through the use of overtime. The cost would be only $2,500.

Should the company do it? Why or why not?