Question: 20. You're managing a software project, when your customer informs you that a schedule change is necessary. Which is the BEST thing to do? A.
20. You're managing a software project, when your customer informs you that a schedule change is necessary. Which is the BEST thing to do? A. Consult the schedule management plan. B. Notify the team and the sponsor that there's going to be a schedule change. C. Influence the factors that cause change. D. Refuse to make the change because there's already a schedule baseline.