Question: A three-phase (34.5-mathrm{kV}) feeder supplying a 4-MVA load is protected by (80 mathrm{E}) power fuses in each phase, in series with a recloser. The time-current
A three-phase \(34.5-\mathrm{kV}\) feeder supplying a 4-MVA load is protected by \(80 \mathrm{E}\) power fuses in each phase, in series with a recloser. The time-current characteristic of the \(80 \mathrm{E}\) fuse is shown in Figure 10.43. Analysis yields maximum and minimum fault currents of 1000 and \(500 \mathrm{~A}\), respectively.
(a) To have the recloser clear the fault, find the maximum clearing time necessary for recloser operation.
(b) To have the fuses clear the fault, find the minimum recloser clearing time. Assume that the recloser operating time is independent of fault current magnitude.

FIGURE 10.43 Problem 10.16 Time in seconds 0.5 0.3 Current limiting 80E power fuse 34.5 kV 60 Hz 25" C ambient 0.2- Maximum clearing time 0.1 0.06 1 0.03 Minimum melting time 0.02 0.01 300 500 1000 2000 5000 Current in amperes
Step by Step Solution
3.48 Rating (155 Votes )
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts